Section 3: Installing the Instrument
05/11 17 51209 Revision 2
3
Installing the Instrument
• Before starting work, please read Chapter 1 and follow all instructions.
Further procedures:
• Check the consignment: unpack the components specific to the application.
• Safety check: inspect all components for damage.
• Make sure the on-site installation is correct and complete including cables, e.g. power cable fuse
protection, load cells, cable junction box, data cable, console/cabinet, etc.
• Follow the instructions for installation of the unit relating to application, safety, ventilation, sealing
and environmental influences.
• Connect the cable from cable junction box or platform/load cell.
• If applicable: connect other data cables, network cables, etc.
• Connect the instrument to the supply voltage.
• Check the installation.